This fence estimate template is built for fence and general contractors. It starts with the lines a wood fence bid actually carries (tear-out, posts, concrete, rails, pickets, hardware, gate, labor), lets you enter your cost for each, adds your markup and shows the margin it gives you, and prints a client-ready estimate with inclusions, exclusions and signature lines. Need something for the clipboard? Print the blank form. A full worked example for a 164 ft privacy fence is below.
Free to use. No signup needed.
How to Fill Out a Fence Estimate
The takeoff math, 2026 price checks, markup vs margin, and a complete worked fence bid.
What Goes on a Fence Estimate?
A fence estimate lists the fence spec, the takeoff, the price and the terms. The spec says what the client is buying: material, style, height, total linear feet, post spacing and every gate with its width. The line items carry tear-out, posts, concrete, rails, pickets or panels, hardware, gates and labor. The terms cover what is included, what is not, the deposit and how long the price is good for.
- Tear-out and haul-off of the old fence, per linear foot
- Posts counted by run: line, corner, end and gate posts
- Post concrete in bags, from the hole size
- Rails, pickets or panels, with waste on pickets
- Gates as their own lines: frame, hardware, hanging
- Labor, per linear foot or from crew hours
- Permit if your city requires one, passed through at cost
- Exclusions: survey, sprinkler lines, rock beyond an allowance, stain
The spec block matters more than most contractors think. Two bids for "a 6 ft wood fence" can be for completely different fences. Spelling out post size, spacing, rail count and picket type is how the client compares your bid to the cheaper one fairly.
Key Takeaways
- Spec block: material, height, linear feet, post spacing, gates
- Gates get their own line items
- Exclusions protect you when the auger hits rock
How to Do the Fence Takeoff
Count posts run by run, not from the total footage. Each straight run needs (run length ÷ post spacing) sections, and one more post than it has sections. Corners are shared between two runs, so count them once. Every gate opening needs a post on each side.
- Rails: sections × rails per section (the example below uses 3)
- Pickets: fence inches ÷ picket width. A nominal 1x6 picket is 5.5 in wide, so 1 lf takes about 2.2 pickets butted tight. Add an allowance for culls and cuts (the example below uses 5%)
- Concrete: hole volume minus the post, times the number of holes, divided by bag yield. Quikrete lists a 60 lb bag of Concrete Mix at about 0.45 cu ft and an 80 lb bag at about 0.60 cu ft
Hole depth is set by your local code and frost line, not by habit. Check before you price the concrete, because a deeper hole changes the bag count on every post. Our post hole concrete calculator does the per-hole math, and the fence calculator gives a quick post, rail and picket count to check your takeoff against. For the full estimating walkthrough, see how to estimate fence installation.
Before anyone digs, call 811. It is the free national call-before-you-dig service, and the utilities need a few business days to mark their lines.
Key Takeaways
- Posts per run = sections + 1; count shared corners once
- 1x6 pickets: about 2.2 per linear foot, plus about 5% waste
- 60 lb concrete bag yields about 0.45 cu ft (Quikrete data sheet)
What Fence Work Costs in 2026
Installed wood fence runs about $15 to $35 per linear foot according to Fixr, with wood materials at $5 to $15 per foot and labor at $10 to $20 per foot. Use these ranges to sanity-check your bid, not to set it. Your own supplier prices and crew hours are what the line items should carry.
| Fence type (installed) | Per linear foot |
|---|---|
| Chain link | $12.25 to $40 (Fixr) |
| Wood | $15 to $35 (Fixr) |
| Vinyl | $15 to $40 (Fixr) |
| Aluminum | $15 to $40 (Fixr) |
| 6 ft vinyl privacy | $30 to $55 (Inch Calculator) |
- Gates: Fixr lists $40 to $200 for a standard gate, $50 to $400 installed, and $1,000 to $6,000 for a driveway gate fully installed
- Old fence removal: $600 to $800 for most fences of 100 to 200 linear feet (Fixr), $350 to $600 for basic removal (Inch Calculator)
- Permits: $30 to $200 where required (Inch Calculator). Not every city requires one, so check with yours
- Land survey for a boundary fence: $400 to $1,000 (Fixr)
Prices vary by region. Labor rates, lumber prices and permit rules change from one county to the next, so price from your local supplier and your own crew, and tell clients to get more than one bid on the same spec. The fence installation cost calculator adjusts a per-foot range by ZIP code if you want a second check.
Key Takeaways
- Wood fence: $15-$35/lf installed, $10-$20/lf of that is labor (Fixr)
- Permits $30-$200 where required (Inch Calculator)
- Prices vary by region; price from your own supplier and crew
Markup vs Margin on a Fence Bid
Markup is a percentage of your cost. Margin is a percentage of the price. They are not the same number, and mixing them up is an easy way for a fence bid to come in thin. To hit a target margin, divide your cost by (1 minus the margin).
- Want 25% margin? Price = cost ÷ 0.75, which is a 33.3% markup
- Want 30% margin? Price = cost ÷ 0.70, which is a 42.9% markup
- A 25% markup only gets you a 20% margin
To reproduce the worked example below in the template, type 33.33 in the markup box (it shows $5,717.86, a few cents under the $5,718 from dividing by 0.75). The template shows the margin next to the markup you type, so you can see what you are actually keeping. The contractor markup calculator works it either direction. Markup has to cover overhead (truck, insurance, office, the hours spent bidding) before any of it is profit.
Key Takeaways
- Price = cost ÷ (1 - target margin)
- 33.3% markup = 25% margin
- A 25% markup is only a 20% margin
Worked Example: 164 ft Wood Privacy Fence
A 6 ft wood privacy fence with one 4 ft walk gate comes to $5,718 in this example, about $34.87 per linear foot all in. The yard has a 96 ft back run and two side runs of 32 ft and 36 ft. The 36 ft side holds the gate, so there are 164 lf in total and 160 lf of fence. The old fence being torn out is also 160 lf.
Takeoff (posts 8 ft on center):
- Back run: 96 ÷ 8 = 12 sections, 13 posts (both corners)
- Left run: 32 ÷ 8 = 4 sections, 4 new posts (corner already counted)
- Right run: 4 sections plus the gate, 5 new posts (two are gate posts)
- Posts: 22. Rails: 20 sections × 3 = 60
- Pickets: 160 × 12 = 1,920 in ÷ 5.5 = 349.1, so 350. Plus 5% = 368
- Concrete: 10 in hole, 24 in deep = 1.09 cu ft, minus the 4x4 (0.17 cu ft) = 0.92 cu ft. 22 holes = 20.3 cu ft ÷ 0.45 = 45.0 bags, so order 46 sixty-pound bags. This assumes 4x4 gate posts; heavier gate posts leave the two gate holes needing a little less
| Line (your cost) | Math | Cost |
|---|---|---|
| Lumber and fasteners (blended allowance) | 160 lf × $9 | $1,440 |
| Post concrete | 46 bags × $6 | $276 |
| Fence labor | 160 lf × $10 | $1,600 |
| Tear-out and haul-off | 160 lf × $3.50 | $560 |
| 4 ft walk gate, built and hung | 1 × $300 | $300 |
| Direct cost | $4,176 | |
| Price at 25% margin (33.33% markup) | $4,176 ÷ 0.75 | $5,568 |
| Permit, at cost | $150 | |
| Price to client | $5,718 |
The $9 per foot lumber line is a blended allowance. In a real bid, price the counted 22 posts, 60 rails, 368 pickets and the fasteners from your supplier's quote and divide by 160 to check it; Fixr puts wood fence material at $5 to $15 per linear foot.
The fence itself (lumber, concrete and labor, marked up) comes to $4,421.33, or $27.63 per foot, inside Fixr's $15 to $35 range for wood. If you had added a flat 25% markup instead, the price before the permit would be $5,220 and your margin 20%, which leaves $348 on the table on one small fence.
On the client copy, show each line at its marked-up price so the lines add up to the total: lumber $1,920, concrete $368, labor $2,133.33, tear-out $746.67, gate $400, permit $150. In California the deposit could be no more than $571.80 here, because the state caps it at $1,000 or 10% of the contract, whichever is less.
Key Takeaways
- 22 posts, 60 rails, 368 pickets, 46 bags of concrete
- Direct cost $4,176; price $5,718 with permit
- Cost ÷ 0.75 keeps a true 25% margin
Where Fence Bids Go Wrong
Fence bids usually go wrong below ground. I have been burned underbidding jobs where hidden work blew up once we got into it, and a fence line is all hidden work until the auger goes in. Rock, roots, old concrete footings and buried lines all hide under a nice-looking yard.
- Pricing from total footage instead of counting posts per run, which misses corners and gate posts
- No allowance for rock or old footings. Put a digging allowance on the bid and say how anything past it gets priced
- Gates folded into the per-foot price. A gate has its own frame, hardware and hanging time
- Slope ignored. Stepped or racked panels on a grade take more cutting and more time
- Property line assumed. Write down who marks the line, and that a survey is not included unless it is listed
- No 811 ticket. Write the ticket number on the estimate so everyone knows it was called in
Bidding is not just materials and labor, either. How busy you are, how the client is to work with, and how far the job is from your yard all belong in the price.
Key Takeaways
- Count posts per run, including gate and corner posts
- Carry a digging allowance and price anything beyond it as a change order
- Say who marks the property line
Sending the Bid and Following Up
Send the estimate the same day you walk the fence line if you can, while the measurements and sketch are fresh, then follow up. A lot of jobs are won on the second or third follow-up, not the first estimate. Most contractors send a bid and never chase it, so the one who follows up stands out. The hard part is remembering when you are on a job site all day.
That is why EstimationPro follows up for you, and I use it on my own remodeling jobs. When you send an estimate from EstimationPro, the client gets a reminder at 24 hours if they have not opened it, another 48 hours after they open it if they have not responded, and a final one at 7 days. It builds the line items from your photos, voice notes or typed notes, and it is free to try with 3 estimates and no credit card, then $79 or $149 a month.
Key Takeaways
- Many jobs are won on the second or third follow-up
- Send the bid the same day as the site visit when you can
How to Use This Calculator
Fill In the Fence Spec
Enter your company, the client, the fence material and style, height, total linear feet including gates, and post spacing. This is what lets a client compare your bid to someone else's on the same fence.
Enter Your Cost for Each Line
The template starts with the usual wood fence lines: tear-out, posts, concrete, rails, pickets, hardware, gate and labor. Enter quantity, unit, and your material and labor cost per unit. Rename lines or add more for vinyl panels, chain link fabric, rock allowances or a drive gate.
Add Markup, Permit and Deposit
Type your markup and the template shows the gross margin it gives you. Enter the permit fee if your city requires one (it is added at cost) and a deposit percentage within your state's rules.
Preview, Print or Save as PDF
Preview shows the client copy with each line at its marked-up price, your inclusions and exclusions, and signature lines. Print it or save it as a PDF. Use the blank form button to print a clipboard version for the site visit.
Free to Embed on Your Website
Add this calculator to your blog, resource page, or client portal — just copy one line of code. Your visitors get a useful tool, you get more engagement.
EstimationPro AI For Contractors, By Contractors Go Beyond Templates With AI-Powered Estimates
Templates are a start. EstimationPro generates complete, customized estimates from your project details.
Frequently Asked Questions
What should a fence estimate include?
The fence spec (material, style, height, total linear feet, post spacing, gates and widths), itemized lines for tear-out, posts, concrete, rails, pickets or panels, hardware, gates and labor, the permit if one is required, and the terms: what is included, what is not, the deposit, payment schedule and how long the price holds. Spell out exclusions like a property survey, sprinkler lines and rock beyond an allowance.
How do I count fence posts for an estimate?
Work run by run. Each straight run needs (run length ÷ post spacing) sections and one more post than sections. Count shared corner posts once, and add a post on each side of every gate opening. In the worked example above, a 96 ft run at 8 ft spacing is 12 sections and 13 posts. The fence calculator gives a quick count to check your takeoff.
How many bags of concrete per fence post?
Take the hole volume, subtract the post, and divide by the bag yield. Quikrete lists about 0.45 cu ft for a 60 lb bag and 0.60 cu ft for an 80 lb bag. A 10 in hole 24 in deep around a 4x4 holds about 0.92 cu ft, just over 2 sixty-pound bags, so total all the holes and round up, as in the worked example. Set hole depth to your local code and frost line. The post hole concrete calculator runs it for any hole size.
What markup should I use on a fence job?
Start from the margin you need to cover overhead and profit, then convert it. Price = cost ÷ (1 − margin). A 25% margin needs a 33.3% markup; a 30% margin needs 42.9%. A flat 25% markup only returns a 20% margin. The template shows the margin next to whatever markup you type.
How much deposit can I take on a fence job?
It depends on your state. California, for example, caps the down payment on a home improvement contract at $1,000 or 10% of the contract price, whichever is less, according to the Contractors State License Board. Check your own state's contractor board before you set a deposit.
Related Tools and Articles
Sources
- Fixr: Fence Installation Cost (installed and labor cost per linear foot, gates, removal, survey; opened October 2026)
- Inch Calculator: Cost to Install a Fence (vinyl privacy, removal and permit costs; opened October 2026)
- Quikrete Concrete Mix data sheet (bag yields)
- 811 Before You Dig (free call-before-you-dig service)
- California CSLB: Home Improvement Contracts (down payment limit)
What EstimationPro Does for Contractors
Photos, Voice or Notes In
Describe the job with photos, a voice walkthrough or typed notes and get priced line items for labor and materials. Contractors save 2+ hours per estimate.
Priced for Your Area
Labor and material rates are adjusted for the job's location. You review and edit every line before it goes out.
Automatic Follow-Up
Send the estimate from EstimationPro and your client gets a reminder at 24 hours, 48 hours and 7 days. Many jobs are won on the second or third follow-up.
PDF, Link and Payments
Export a PDF or share a link your client can approve. Collect payments online with Stripe; deposits, milestone schedules and invoices are on Pro.
Related Free Tools
Bid Template
Generate a professional construction bid template. Fill in your project details, line items, and terms to create a downloadable bid document.
Concrete Template
Generate a professional concrete estimate template. Add base, rebar, ready-mix, forms, and finishing labor for a complete concrete bid document.
Handyman Template
Generate a professional handyman estimate template. Add repair tasks, labor hours, materials, and a trip charge for a complete itemized handyman bid.
Deck Template
Generate a professional deck estimate template. Add footings, framing, decking, railing, stairs, and finishing labor for a complete deck bid document.
Drywall Template
Generate a professional drywall estimate template. Add board, tape, mud, corner bead, texture, and finish labor for a complete drywall bid document.
Flooring Template
Generate a professional flooring estimate template. Add tear-out, subfloor prep, underlayment, material, and install labor for a complete flooring bid.
Kitchen Estimate
Generate a professional kitchen remodel estimate. Add cabinets, countertops, appliances, plumbing, flooring, and labor for a complete kitchen bid.
Bathroom Estimate
Generate a professional bathroom remodel estimate. Add demo, plumbing, tile, vanity, fixtures, and labor for a complete bathroom bid.
Turn this job into a full, priced estimate for your client.
Snap photos, talk through the scope, drop in your notes. The AI prices every line item with labor and material rates adjusted for your region, and checks the math.